Summer Works Schedule

 

Summer Works Schedule  

 

Summer works Map 

 

Project Name: Location: Compound Location Contractor Project Manager / E&F Lead Commence Date: Completion Date: Brief Descrption of Works
Demolition of Edith Key & Researcher Hub Queensgate Former Faith Centre D Hughes Demolition Martin Williams 20th July 2024 1st Sept 2024 Demolition of buildings and top soil / grass seeding of resultant area
Southgate 2 - Moortown Enabling Works Southgate Within Southgate 2/3 Site Moortown Mike Charlston 3rd June 2024 21st June 2024 Turning over of the land, to a maximum depth of 3m to de-risk the commencement of main works. Also possible works to create a turning head to the top of Pine Street
Southgate 2 - Main Contract Southgate Within Southgate 2/3 Site Kier Mike Charlston 1st July 2024 12th Dec 2025 Construction of Southgate 2 building
Schwann Building Pipework Replacement Project  Queensgate Wakefield Road Car Park Hensall Ltd Wayne Armitage 20th May 2024 20th November 2024 Replacement of Heating , Chilled Water, Domestic Hot and Cold Water Pipework
Harold Wilson - Repurpose space following H&HS migration to Daphne Steele.  Queensgate TBC TBC Rebecca Smith 19th July 2024 8th November 2024 Space alteration works
Richard Steinitz - Repurpose space following H&HS migration to Daphne Steele and to include the migration of Arts & Humanities migration from Percy Shaw House.  Queensgate TBC TBC Richard Mallinson 19th July 2024 13th Sept 2024 Space alteration works
Daphne Steele Southgate Southgate BAM Paul Riley   12th Sept 2024 Construction of new Building
Ramsden Refurbishment Queensgate Adjacent to Ramsden TBC Mike Charlston TBC - Likely Oct / Nov 2024 TBC - Christmas 2025 Full refurbishment of the building
Re Roofing: Student Central / Joseph Priestley South / Charles Sikes Plant Rooms  Queensgate  TBC  TBC  Mike Charlston / Richard Mallinson October 2024  January 2025 Plan to find areas of weakness and implement roof repairs. 
Charles Sikes - Improving teaching space 3rd floor to allow migration of education.  Queensgate TBC TBC David Lowther / Mike Charlston 19th July 2024 9th August 2024 Space alteration works to allow partial closure of Lockside
Lockside - Work to mechanical systems to allow closure except CPT.  Queensgate TBC TBC David Lowther / Mike Charlston 19th July 2024 9th August 2024 Space alteration works to allow partial closure of Lockside
Student Central PO69 lift replacement Queensgate Wakefield Road undercroft Knowsley Dean Richardson TBC - Likely mid November 2024  TBC - Mid February 2025 Replacment of PO69 lift